Residential Junk Removal and Structure Demolition in Redding, CA
Multiple structures, a mountain of debris and a lot of hauling. Here is how our demolition and junk removal crews handled it, start to finish.
- Redding, CA
- Multiple structures
- 30 and 40 yard dumpsters
- Licensed, Insured & Bonded. CSLB# 1045590
The job at a glance
This one sits in a residential neighborhood on the line between Anderson and Redding, in Shasta County. Our demolition crew and our junk removal crew teamed up to bring down multiple structures of various sizes and haul every bit of them away.
When we first looked at the amount of debris that had to leave, it seemed overwhelming. For a Shasta County junk removal crew with our own 30 yard and 40 yard dumpsters, it was another chance to put those dumpsters to the test, and they held up.
The photos below show where we started and where we finished. The rest of this page is how we got from one to the other, and what it means if you have a property like this in Redding or anywhere nearby.
Here the excavator pulls a wall down above a pile of rubble that is already building up around it. That pile is what the rest of the job was about.

Before and after
On the left, the work in progress: our excavator stands over a pile of broken framing, boards and sheeting, with one wall still standing behind it. Debris like this does not go anywhere by itself.
On the right, the same lot afterward. The structures are gone, the debris is gone, and what is left is bare ground and grass that someone can use again.


What the property needed
A neighborhood lot with more than one building on it asks two different things of a crew. The buildings have to come down safely, and then everything that was a building has to be loaded, hauled and disposed of. Plenty of contractors are good at the first half. The second half is where a job like this either stays on schedule or stalls.
On this property the structures were of various sizes, so the pile was a mix, not one tidy load. The photo below shows the excavator bucket tearing into a wall, and the wood framing, boards and wall panels coming off it are what had to be loaded and hauled. It was a heavy hauling job from the start, and we treated it as one.
That is why the demolition crew and the junk removal crew worked the lot together. One tears down, the other keeps the debris moving. Neither waits on the other, and the lot never fills up with material that has nowhere to go.

What we did
Walked the lot and planned the loads
We looked at each structure, where the machine could stand, and where the dumpsters could sit so the debris had a short trip from the pile to the bin. On a residential lot, that placement decides how smoothly the whole day goes.
Brought down the structures
Our excavator operator took the structures apart one at a time. The first photo above shows the machine in the middle of it.
Sorted as we went
The debris was sorted while it came down instead of afterward. Separating wood, metal and loose material early makes each load cleaner and keeps the pile from growing into one big mixed heap.
Loaded and hauled
The excavator loaded building debris into our dumpsters, and the crew raked the ground clear around it so the next bucket had somewhere to work. Moving debris is steady, physical work, and it is the half of a demolition that customers rarely see.
Cleaned up the lot
When the last structure was down and the last load gone, we went over the ground so the lot was left clear, as the second photo shows.
The equipment and dumpsters we used
The machine in the photos is our excavator. It does the heavy teardown and also lifts and stacks debris so the crew can load faster than they could by hand. In the first photo below its bucket is releasing building debris into a dumpster; the second shows a roll-off dumpster on the worksite with the excavator at work behind it, and the third our roll-off truck with its hoist raised.
The hauling ran on our own roll-off dumpsters, in the 30 yard and 40 yard sizes. They are the two larger sizes on our dumpster rental list, and a job with this much debris is what they are for.
A 30 yard dumpster is 22 feet long, 8 feet wide and 6 feet tall, and the rental price of $550 a week includes 3 tons. The 40 yard is the same footprint but 8 feet tall, at $650 a week with 4 tons included. Extra weight beyond the included tons is $110 a ton, and each extra day is $10.



Which dumpster size fits which kind of pile
Pick by volume first and weight second. A 30 yard dumpster is a good fit when the pile is large but mostly light, like framing and boards. The 40 yard is the choice when the volume is the problem, because its 8 foot walls hold the most.
Heavy material changes the math. Concrete and dirt weigh far more than they look, and they can use up the included tons well before the dumpster is full. If your lot has any of that, tell us at the estimate so we plan the load and the bin around the weight instead of guessing.
The 20 yard dumpster, at $450 a week with 2 tons, is the lowest-sided of the three and suits a smaller cleanout. For a multi-structure lot, the 30 and 40 yard sizes are where the conversation starts.
The cleanup and haul-off
A demolition is not finished when the building is down. It is finished when the lot is clear. That is why the haul-off is part of the work and not an add-on.
Loads have to be tarped: the City of Redding charges double at the gate for an untarped load, so covering the haul is part of doing it right. Disposal then happens at the city or county facilities, and the gate fees there are set by the facility, not by us. We list the current fee sheets below so you can see where the numbers come from.
The photo here shows crew members raking the demolition debris on the lot, with the excavator behind them. When we leave, the ground should look like the cleared lot in the last photo below: no stray boards, no half-buried pieces, nothing left for the owner to deal with. If you are weighing a cleanup like this against doing it yourself, the hauling is what takes the time and the equipment.

Source: City of Redding: rates and fees, City of Redding: landfill gate fees
The result
The owner was left with an open, cleared lot in a Redding neighborhood where multiple structures used to stand, with the debris gone and the ground ready for whatever comes next.
The wide photo below shows the cleared lot afterward: bare, worked ground with grass around it, and one small shed left standing at the back.
If you have a lot like this, a free estimate will tell you what it takes. You can call (530) 276-8755 or send the form, and we will look at the structures and the debris and tell you the plan.

How a multi-structure demolition works in Redding
Start with the permit. Inside the city, the Building Division at the Permit Center, 777 Cypress Ave, handles demolition permits, open Monday to Friday, 8 am to 3 pm. A lot in the county, outside the city limits, goes through the Shasta County Building Division instead. A neighborhood on the Anderson and Redding line can fall on either side of that boundary, so check which one your parcel is in before anything else. This is general context, not legal advice.
The City of Redding also requires a refundable construction waste deposit before it issues a building permit, effective October 18, 2026: $500 for a residential demolition. It is refunded against weight tickets from the Redding Transfer Station, so keep every ticket and ask the building division for the current steps.
Utilities come next. A home scheduled for demolition has its PG&E service cut and capped at or outside the property line, so that is arranged before the machine arrives. In Redding, electric service is the city-owned Redding Electric Utility, and its number is 530.339.7200.
Small buildings are the exception. The city says a one-story detached tool or storage shed up to 120 square feet needs no building permit, though Planning review generally still applies. Anything larger than that is a permit conversation.
Source: City of Redding: building division, City of Redding: permit FAQs, PG&E: residential project resources
Where the debris goes
Debris from a Redding job lands at a handful of places. The Redding Transfer Station, at 2255 Abernathy Ln, is open Monday through Saturday, 8:00 to 4:30. It does not accept dirt, rocks, concrete, asphalt or stumps with dirt.
West Central Landfill, at 14095 Clear Creek Rd in Igo, is owned by Shasta County and run by Redding's Solid Waste Utility, and it takes waste from all of Shasta County. Concrete, asphalt, bricks and stumps are accepted there as demolition debris. Paint, oils and treated wood are not.
On the Anderson side, the Anderson Landfill at 18703 Cambridge Rd is open Monday to Friday 7:00 to 3:30 and Saturday 7:00 to noon. It takes non-friable construction and demolition debris, yard waste, mattresses, e-waste and tires.
Sending a mixed load to the wrong place costs time and money. Part of what you hire a crew for is knowing which facility takes which part of the pile.
Source: City of Redding: transfer station fees, Anderson Landfill fact sheet
Why one crew for the teardown and the hauling matters
Many properties end up with two contractors: one to demolish and a second to haul. Each one waits on the other, and the debris sits in between. On a residential lot, the neighbors see that pile every day it stays.
On this job the machine fed the dumpsters directly, and the loads left full while the teardown went on. The same crew can also do the cleanouts that come before a demolition, so the buildings are empty before they come down. Our construction site cleanup page covers the hauling side of a build.
Questions from Redding property owners
Do you handle both the demolition and the junk removal? Yes. This job is the example: the same company took the structures down and hauled the debris, with our own dumpsters.
How do I know which dumpster size I need? Describe the pile at the estimate and we will recommend one. Volume points to the 40 yard, and heavy material points to checking the included tons first.
Do I need a permit? For structures that are not exempt, in most cases yes, and the building department that issues it depends on whether the parcel is in the city or the county. We explain the steps at the estimate and link the city and county pages above.
Serving Redding and the rest of Shasta County
We take on demolition, junk removal and dumpster rentals across Redding and the rest of Shasta County, from the neighborhoods along the Anderson line to the towns farther out.
If you have structures to take down, a property to clear or a pile that needs a dumpster, start with the Redding page, which lists the local rules in one place, or call for a free estimate.
More about this work
- Construction site cleanup
- Roll-Off Dumpster Rentals
- Service area: Redding
- Mobile home removal in Millville
- Multi-structure demolition and property cleanup in Bella Vista
- Mobile home removal in Shasta Lake
- House demolition and fire fuel removal in Cottonwood